US Denim

Utility and Generator Synchronizing, Load-sharing and Baseload Control and of 04 GEN-SETS for Main Power plant.

Problem

US Denim decides to add efficient 5MW Electrical Power Generation and upgrade the existing control system due to its plant expansion and load requirement. For the power requirement, they Install 2 CAT Gas Generators. Continuous and uninterruptable Power is the first preference for the Textile and Denim industry. Enercon was chosen for the job as it is a proven renowned name & leader in customized Power generation Controls.

Solution

Enercon Systems International (Pvt.) Ltd supplied 1x Master Panel including existing GE Engine (Jenbacher) Control/Synchronization and 2 Generator Control Panel, Our scope include Mater panel with Synchronization System for 2 X Jenbacher engine and Utility Synchronization, Control Panel for 2X 3520H, interfacing and load sharing with 2x Jenbacher Engine and 4XCAT diesel engine which running with ComAp.

Challenge

Need complete Generator Control, Synchronization, and up-gradation of old Synchronization control, this was the Prime source of power for complete 4 Units for US Denim.

Other Projects

EBM

Successfully achieved an Energy Monitoring & Management Solution for one of the

MONDELEZ

Successfully delivered a comprehensive Industrial Automation & Energy Management solution for a

US Denim